Star ProductsMedium and High Voltage SwitchgearLow Voltage SwitchgearSubstationsPower Distribution BoxesAuthorized CabinetsPhotovoltaic CabinetsGas-Insulated CabinetsBuswaysComprehensive Training Building (EPC) ProjectEPC Engineering of Du'an People HospitalEPC Project of Teng County Industrial Park40.008MWp Distributed Photovoltaic ProjectPower Engineering General ContractingBYD's Phase III Power Distribution ProjectNanning Qingxiu Tesla Center Power DistributionGaoshan Operation Area Power Distribution ProjectGuida Paper 35kV Substation EngineeringIron & Steel Base Power Distribution Project10kV Power Distribution Project for Cold StorageIndustryBeitou Yinshan Power Distribution ProjectPower Distribution Project of Hezhou Binfen MallLiuzhou CR Land Power Distribution ProjectGuangxi MYJ Industry Power Distribution ProjectPower Distribution Project of Creative ParkCommercial Real EstateIndustry - Education Integration Power SupplyYao Medicine Hospital Power Distribution ProjectMuseum Power Distribution ProjectSurveying & Mapping Bureau. Power Distribution ProIntegration Training Building Power DistributionGX Agricultural Vocational and Technical UniversitNanning University Training Building Power DistribGX Agricultural Engineering Vocational and TechnicPujin Road Phase II Sewage Pipe Box-type SubstatioInfrastructureBaise Sports Center Charging Piles Power DistributNapo People's Court Charging Piles Power DistributSmart Park Charging Piles Power Distribution ProjeEnergy and PowerPower Distribution Project of Nanning Rail TransitTian'e-Beihai Highway Power Distribution ProjectGuanyang - Pingle Mechanical & Electrical EngineerTransportation1.92MW Distributed Photovoltaic Power ProjectPhotovoltaic Power Generation Project (Phase I)Agriculture, Forestry, Animal Husbandry & FisheryProjects OverviewNews CenterVideo UpdatesIndustry FAQIndustry White PaperGroup ProfileIndustrial Products Platform QiansimaiHonors and QualificationsSeeking Overseas Distributors
概述

南宁职业技术大学相思湖校区产教融合综合实训楼(EPC)工程

南宁职业技术大学相思湖新校区产教融合综合实训楼建设工程,需建设配套10kV配电设施。


项目核心要求:

− 紧急工期:合同约定15天内完成高压设备安装及电缆试验;

− 设备配置:采用两台ZBW-12智能箱式变电站+一台户外开关箱;

− 环境条件:南宁地区属亚热带气候,日平均湿度≤95%。


应用产品

户外开关箱、箱式变电站

解决方案
客户痛点

方案主张

客户价值

1. 设备选型


三位一体设计:集成高压柜(可选真空断路器)、变压器(S11型油浸式)、低压柜(智能断路器),减少现场拼装环节。


环境适应性:

▶ 蜂窝式双层复合外壳(冷轧板基材),防护等级IP54;

▶ 高压室配置温湿度传感器(依据说明书“可装配配网自动化终端”功能扩展能力)。

扩展兼容性:预留配网自动化终端(FTU)槽位,支持未来升级。

空间集约化:箱式变电站户外部署免除独立配电房建设。


本质安全提升:

− 开闭所可触摸电缆头消除触电风险;

− KYN28柜体五防联锁杜绝误操作。

运维效率优化:

− 箱变状态远程监控减少现场巡检;

− 开关柜手车结构缩短设备维护时间。


可持续扩展:开闭所多回路设计预留负荷扩容能力。

2. 交付流程优化


工厂预装调试:箱变内部连线在出厂前完成,减少现场工时;

并行施工:设备基础与电缆敷设同步推进。

1. 工期极短


常规变电站施工周期需1-2个月,但教学进度要求15日交付。

2.空间受限


设备放置于室外,需户外紧凑型设备;

3.环境挑战


高湿度环境易导致电气设备凝露、绝缘下降。