10kV Power Distribution Project for Cold Storage Capacity Expansion (Substation #2) of Nanning Weining Supply Chain Project
The Nanning Weining Supply Chain Project is located south of Naping Road and west of Nama Avenue in Liangqing District, Nanning, serving as critical local cold chain logistics infrastructure. To meet the power demand of the cold storage capacity expansion, the project required the construction of Substation #2 and the implementation of a 10kV power distribution工程. This ensures a stable and reliable power supply system compliant with the utility company's acceptance standards. The project encompasses full-scope services including power application, drawing design, equipment installation, external line construction, cable trench construction, floor treatment, and system commissioning, representing a typical "turnkey" power distribution system project.
Siwu Solution
Customer Value
Rapid Delivery Assurance
Professional integrated management shortens the construction period, supporting the on-schedule progression of the cold storage expansion plan.
Long-Term Operational Reliability
Strict adherence to power distribution standards during construction and commissioning minimizes the risk of cold storage operational interruptions due to power distribution issues.
Stringent Acceptance Standards
One-time approval from the utility company was required, where any oversight in details could lead to increased rectification costs and project delays.
Compliance & Peace of Mind
One-time passing of utility acceptance avoids subsequent rectification investments, providing the client with a compliant and safe power usage environment.
Complex Project Phases
Involvement of multiple coordination stages (application, design, construction, acceptance) meant traditional subcontracting models easily led to unclear responsibilities and project delays.
Environment-Adaptive Design
Enhance moisture protection for cable trenches and grounding system protection tailored to the humid southern climate, ensuring long-term stable equipment operation.
Collaborative Management Mechanism
Efficiently coordinate the schedule between client-supplied equipment (HV/LV switchgear, transformers, etc.) and the contractor's construction progress, ensuring seamless integration of conduit embedding and equipment installation.
Controlled Costs
The lump-sum turnkey model avoids additional change-order costs and reduces the client's coordination efforts during construction.
High Requirements for Equipment-Environment Compatibility
The substation needed to adapt to Nanning's high-temperature and high-humidity environment, demanding higher technical specifications for busway, cable trench moisture resistance, and insulation protection.
Full-Scope Turnkey Service
Provide a "one-stop" solution from application and design through construction and acceptance, clarifying responsibility boundaries and avoiding risks associated with multi-party management.
Standardized Construction & Material Specifications
Utilize standardized materials such as epoxy floor paint, insulating mats, and fire stopping to ensure processes like cable trench construction and busway installation comply with safety codes.
|
|